Monthly Archives: January 2014

//January
­

Airport of Tasiast

AGS – Protección Medida y Control has completed the supply, installation and commissioning of the Runway Lights at the newly renovated Airport of Tasiast (Mauritania), located in the Tasiast gold mine for our client Kinross Gold Corporation. Despite having to carry out the installation and commissioning against the clock to meet the customer needs, AGS [...]

By |January 28th, 2014|news|0 Comments

AGS, in collaboration with GE Multilin, has performed the secondary test commissioning of the GCPPs related to the generators A, B and C on the LNG DONGGI SENORO Plan

AGS, in collaboration with GE Multilin, has performed the secondary test commissioning of the GCPPs related to the generators A, B and C on the LNG DONGGI SENORO Plant (propriety of DONGGI SENORO), in Uso / Luwuk Indonesia. AGS-PMC 100% has started the project from the beginning (2013) and it will fulfill at the end [...]

By |January 16th, 2014|news|0 Comments

AGS, has collaborated with General Electric NP, in the FAT (Factory Acceptance Test) in the Hebron´s Projet.

Hebron is a heavy oil field estimated to produce more than 700 million barrels of recoverable resources. The field was first discovered in 1980, and is located offshore Newfoundland and Labrador in the Jeanne d’Arc Basin 350 kilometres southeast of St. John’s, the capital of Newfoundland and Labrador. It is approximately 9 kilometres north of [...]

By |January 13th, 2014|news|0 Comments

AGS, has collaborated with General Electric NP, in the FAT (Factory Acceptance Test) in the Ichthys´s Projet.

Total and its joint venture partner INPEX Corporation announced that they have taken the final investment decision for the Ichthys liquefied natural gas (LNG) project in Australia, representing an investment of US$34 billion dollars. Total holds a 24% interest in the project which will develop approximately 3 billion barrels oil equivalent of reserves, including around [...]

By |January 13th, 2014|news|0 Comments

Secondary injection in GCPP (Control panels and generator protection).

DSLNG Donggi Senoro (Nuovo Pignone GE / JGC JAPAN GAS COMPANY) AGS, in collaboration with GE Multilin, completed the secondary injection in GCPP (Control panels and generator protection) generators A, B and C DLNG Donggi SNORO (property Donggi Senoro) project located Uso, Luwuk , Indonesia. AGS has completed the project early in 2013, and until [...]

By |January 13th, 2014|news|0 Comments

Startup of a generator in Hugoton’s biomass power plant situated in Kansas

AGS – Protección Medida y Control, in collaboration with General Electric MULTILIN, finished the startup of a generator in Hugoton’s biomass power plant situated in Kansas State in the United States of America. The power plant itself produces ethanol and, on the other hand, cogenerates to produce electric power, generating 22 MW. AGS’s mission was [...]

By |January 13th, 2014|news|0 Comments

Generator protection primary tests on a steam turbine in Hugoton 22 MW biomass power plant

Generator protection primary tests on a steam turbine in Hugoton 22 MW biomass power plant, situated in Kansas (USA).

By |January 9th, 2014|news|0 Comments

Final testing on 5 Gas Turbines (Nuovo Pignone GE)

AGS in collaboration with GE Multilin, has finished all activities in a billionaire project LNG Train Plant (propriety of Sonatrach), in Skikda Algiers. LNG trains: LNG trains perform the converting process of the natural gas into liquid gas to facilitate maritime transport. AGS-PMC 100% has engaged in the project from the beginning (2011), reserving some [...]

By |January 9th, 2014|news|0 Comments