Project Description

DSLNG DONGGI SENORO (Nuovo Pignone GE/JGC JAPAN GAS COMPANY)
AGS, in collaboration with GE Multilin, has performed the secondary test commissioning of the GCPPs related to the generators A, B and C on the LNG DONGGI SENORO Plant (propriety of DONGGI SENORO), in Uso / Luwuk Indonesia.
AGS-PMC 100% has started the project from the beginning (2013) and it will fulfill at the end of the year 2014. Since the first moment AGS has been overtaken all the difficulties and delays in a way to reach the milestones and following the schedule such in this kind of project is quite important as a big delay means a big waste of money and AGS is always looking for the maximum profit for his clients and the success.
That´s why GE Multilin, once again, have trusted in AGS-PMC to develop the commissioning of the project from the start.